All Points’ Culpeper project called ‘abject failure’
An “abject failure” is how one Culpeper County Supervisor characterized the county’s broadband project with All Points Broadband. At a January 2025 board meeting, All Points Senior Vice President of Business Development Tom Innes gave an update on the project, one that was extremely similar to the one he gave in November even though the company has a contracted deadline to be 80 percent complete with the project by the end of February. Innes admitted that All Points will not meet the February deadline, citing a large backlog of permits. Supervisor Tom Underwood said the permits themselves are riddled with issues. He said in one area, at least seven permits are in areas that are under prescriptive easements. “APB has been an abject failure,” Underwood said. “I am not in favor of an extension [and] I’m not in favor of accepting money to underground [fiber] when you haven’t done the work.”